Headley Court – mains renewal
SES Water has already delivered a mains replacement programme in the Headley area, located to the south of the new development on The Drive. The main has been renewed along the entire length of Church Lane and Headley Common Road up to the junction with Pebble Hill.
We are now installing approximately 782 metres of new main from the junction of Hurst Drive, along Clay Lane, Tilley Lane, and Headley Road, finishing at The Drive.
This upgrade will also support the new development on The Drive and increase the capacity of the local network, improving the long-term reliability of the drinking water supply in your area.

Properties along the route will be connected to the new main, after which the old pipe will be safely taken out of service to complete the upgrade.
Timings
The work onsite commences on the 22 January and we expect to complete this by the 12 April.
To keep everyone safe during the works, we’ll be using a combination of road closures and temporary traffic lights, we will maintain access to properties however there may be occasional short delays with a diversion route in place.
If you have any questions, please contact your SES Water Customer Liaison Officer who will be happy to help.
Tracey Buckland on 07368 504785 between 8am and 5pm, Monday to Friday (excluding bank holidays).
Road closures and traffic management